Minister of Energy Almasadam Satkaliyev held a meeting with the population of Almaty
24.12.2024 22:18:38 1013
During the meeting, the minister informed the residents of the city about the measures taken by the department for the development of the oil and gas and energy industries.
Thus, the level of gasification in Almaty is 100%, and about 2 million people have access to gas.
The power plants of the Almaty region and the city of Almaty have generated 6.7 billion US dollars this year. kWh of electricity, with domestic consumption of 11.7 billion. kWh.
The average physical wear of the main equipment of AlES stations ranges from 73 to 85%.
The regional electric grid company Alatau Zharyk Companiyasy JSC has 8,528 km of cable and overhead power lines in its assets. The company has 2,748 substations on its balance sheet. The physical depreciation of the electric grid is 88.8%.
Major repairs of the power plants of AlES JSC are carried out in accordance with the schedule.
"In 2024, repairs were carried out in the amount of 1.8 billion tenge.
There is a decrease in the accident rate of the main equipment compared to 2022-2023. As part of the solution of environmental issues of the city, AlES JSC is implementing a project to convert thermal power plants to gas.
The complete conversion of Almaty CHPP-2 to gas is planned to be completed in 2026. The implementation of the project will ensure a reduction in emissions of harmful substances from CHP-2 from 37.3 to 2.7 thousand tons per year," the minister said.
Issues are being worked out to cover the gas shortage in the region.
Today, gas consumption in the city of Almaty and the Almaty region during peak periods is up to 800 thousand m3/hour, which is the maximum under the current scheme and condition of the gas pipeline in the southern region.
The growth of gas consumption in the region in the near future is expected to reach 2 million m3/hour, taking into account the gasification of the Almaty thermal power plants.
In order to provide the gas transportation infrastructure of the Almaty CHPP, design and estimate documentation is being developed for the construction of the TIP-04 bridge between the Kazakhstan-China and Almaty-Bayserke-Talgar main gas pipelines, the 2nd line of the Almaty-Bayserke-Talgar main gas pipeline, and the AGRS for CHPP-2 and CHPP-3.
"All the issues raised are under constant control of the Government," the minister concluded.
The participants of the meeting asked all their questions and received comprehensive answers to them.

Source : https://www.gov.kz/memleket/entities/energo/press/news/details/908356