Projects to modernize water supply systems are being implemented in Mangystau region
15.02.2025 00:09:12 407
During his working trip to Mangystau region, Vice Minister of Industry and Construction of the Republic of Kazakhstan Kuandyk Kazhkenov visited several facilities related to the modernization of water supply and water treatment systems.
As part of the trip, the construction and modernization of a number of important infrastructure projects aimed at improving water supply to settlements were inspected.
In order to fulfill the President's instructions, a desalination plant is being built in the Kenderli resort area, which will produce 50 thousand m³ of water per day.
The project is divided into two complexes: a desalination plant with external engineering infrastructure networks and internal engineering networks. Currently, the construction of engineering and communication infrastructure has been completed. The buildings of the desalination plant have also been constructed. The launch is planned for May 2025, which will provide uninterrupted water supply to the city of Zhanaozen and nearby settlements.
Since 2019, a project to increase the capacity of the "Caspian" desalination plant from 20 thousand m³ to 40 thousand m³ per day has been implemented. Currently, the process of processing acceptance documents is underway. The increase in the plant's capacity will allow providing additional water to the population of Aktau and the Munayly district.
Since 2023, the construction of a desalination complex with a capacity of 5 thousand m³ of water per day has been underway in the city of Fort-Shevchenko. The work is scheduled to be completed in March 2025. Currently, the main construction and installation works have been completed, and commissioning and maintenance work is underway.
Also, the construction of sewage treatment facilities No. 2 (STP-2) in Aktau has been underway since 2023, with a capacity of 40 thousand m³ per day. Reinforced concrete works are 95% complete, equipment has been delivered to the facility. The work is being carried out according to plan, the project will be commissioned in September 2025.
During the working visit, Kuandyk Kazhkenov got acquainted with the progress of the projects, gave relevant instructions to the responsible persons, and also noted the importance of completing all work on time. The implementation of these projects will significantly improve the water supply system of the region, provide the population with high-quality drinking water, and increase the standard of living of the population.

Source : https://www.gov.kz/memleket/entities/mps/press/news/details/937238