Akim of Saran: "We are working to create reliable infrastructure"

Akim of Saran: "We are working to create reliable infrastructure"

21.02.2025 01:50:29 594

This year, the modernization of housing and communal services in Saran will continue. The city is actively developing: residential buildings are being restored, new facilities are being opened. Accordingly, the infrastructure must comply with these changes.
The mayor of Saran Daryn Bulkayr told about what work was done in the housing and communal services sector of Saran last year and what will be done this year at a briefing organized by the Regional Communications Service.
Last year, great work was carried out to modernize the housing and communal services, and in 2025 the city expects even more significant changes.
- Our main task is to ensure the uninterrupted operation of all vital systems of the city. The issue of heat supply is under special control, - noted the mayor of Saran Daryn Bulkayr.
Today, 113 apartment buildings are heated by a central boiler house, and another 160 houses by local boiler houses. This year, 57 houses and 27 social facilities will be connected to the central heating system. The work will be carried out in stages, depending on the readiness of the houses and internal pipelines.
The reconstruction of water supply networks in the city will continue. Last year, 28 km of main and 20 km of sub-urban networks were built. Work was completed in the Ugolny settlement, and in other areas it is still ongoing. In 2025, houses should be connected to the new networks.
In addition, a reservoir is being built at the second water lift with a volume of 10 thousand cubic meters.
- It will allow creating a drinking water reserve and ensuring uninterrupted water supply, - the akim noted.
In connection with the restoration of houses in the RTI district, the development of the GMS for the construction of main networks of water supply, drainage, reservoir and lifting pumping station has begun.
Also, electrical networks are being modernized in Saran: 9 feeders and 52 km of ownerless networks were transferred to the city balance. This year, it is planned to replace feeders, increase the cable cross-section and install new lighting poles. A large-scale project to modernize electrical networks is also being completed in Aktas. All these works should improve the quality of electricity transmission.
The sewerage networks were also not left without attention - 35.5 km of reconstruction is planned. The work will be carried out in three stages.
- The city is growing, new facilities are emerging, and the networks must bear the load. We are working to create a reliable infrastructure, - noted Daryn Bulkair.

Source : https://www.gov.kz/memleket/entities/karaganda/press/news/details/937994