Construction of main ethane and propane pipelines begins in Atyrau Region

Construction of main ethane and propane pipelines begins in Atyrau Region

16.11.2026 14:11:10 336

Construction has begun in Atyrau Region on main ethane and propane pipelines that will connect the gas separation complex at Tengiz with petrochemical plants in the National Industrial Petrochemical Technopark Special Economic Zone (SEZ) in Karabatan.

Akim of Atyrau Region Bolat Aksholakov attended the launch ceremony. He noted that developing the petrochemical industry and deep processing of raw materials would help expand industrial production in the region.

“Today, it is important not to limit ourselves to extracting raw materials, but to develop their deep processing and manufacture finished products with high added value. This project will enable the development of new industries, attract investment and create jobs, while polyethylene and polypropylene production will open up new opportunities for small and medium-sized businesses. Our goal is to transform the region into a major industrial hub with modern petrochemical facilities,” Bolat Aksholakov said.

During the event, a three-party memorandum was signed between the Department of Employment Coordination and Social Programmes, KMG PetroChem LLP and the contractor, ChPPI Kazakhstan LLP, providing for priority employment opportunities for local residents. Up to 1,300 jobs are expected to be created at the peak of construction, with around 170 permanent jobs once the pipelines are commissioned.

According to Artur Konyskaliev, Deputy Chairman of the Management Board of KMG PetroChem LLP, both pipelines will be approximately 210 kilometres long and laid within a shared technical corridor. The ethane pipeline will have an annual transportation capacity of 1.6 million tonnes, while the propane pipeline will carry 1.1 million tonnes. Ethane will be supplied to the polyethylene plant, and propane to the propylene production facility. The company plans to engage local specialists and Kazakhstani businesses in the project.

Construction is scheduled for completion by the end of 2028. The seamless carbon and alloy steel pipes are designed to withstand low-temperature operating conditions. Production of pipes for the propane pipeline has already begun.

Source : https://www.gov.kz/memleket/entities/atyrau/press/news/details/1316166?lang=ru