A heating main with a length of almost 6,000 m has been completely replaced in Almaty

A heating main with a length of almost 6,000 m has been completely replaced in Almaty

16.11.2024 18:32:33 1001

In Zhetysu district in the MD. Ainabulak completed the reconstruction of heating networks, which was commissioned by Almaty Thermal Networks LLP two years ago. The total length of the heat supply networks is 5865 m.
In 2022, 1,730 m was reconstructed, in 2023 - 2000 m and in 2024 - 2,135 m–
This year, reconstruction has been completed on the segment of the TM-18 "Ainabulak" heating main along Makatayev Street (from Zhumabayev Street to Pavlodarskaya Street).
The main construction and installation works were completed before the onset of the autumn-winter period 2024-2025.
Currently, the landscaping of the site is underway – asphalting the roadway with a fine-grained layer, after which road markings will be applied.
It should be noted that the heating main was put into operation in 1981, its service life was 43 years, while the standard service life is 25 years.
The project will provide high-quality heat supply to residents of 344 apartment buildings, 11 schools, 3 health facilities and 483 other facilities.
This year, on behalf of Akim of Almaty Yerbolat Dosayev, 20 km of heating networks were reconstructed, work was carried out in 6 districts of the city during the inter-heating period. Landscaping of the sites after reconstruction is carried out in stages, depending on weather conditions.

Source : https://www.gov.kz/memleket/entities/almaty/press/news/details/878050