Auction results for the type of hydroelectric power plant with a total installed capacity of 20 MW
16.11.2024 18:57:50 1817
On November 14, 2024, auctions for renewable energy were held for all zones of the UES of the Republic of Kazakhstan (with the exception of the Republic of Tatarstan).Tentek) for the selection of projects for the construction of hydroelectric power plants with a total installed capacity of 20 MW.
5 companies were allowed to participate in the auction, and 11 price offers were submitted by the participants during the trading session. The declared total capacity from the auction participants amounted to 23.23 MW.
The maximum auction price during the auction for the selection of HPP projects in 2024 was 41.23 tenge/kWh (excluding VAT). The decrease in the price range of applications was from 41.23 to 38 tenge/kWh (excluding VAT).
The winners of the auction:
Smart Energy LLP installed capacity of the project is 1 MW, auction price is 38 tg/kWh (without VAT);
Koksu Kuat LLP the installed capacity of the project is 4.2 MW, the auction price is 39.99 tenge/kWh (without VAT);
Cascade Karatal HPP LLP installed capacity of the project is 9.9 MW, auction price is 40 tenge/kWh (without VAT);
Smart Reenergi LLP installed capacity of the project is 1 MW, auction price is 40.01 tenge/kWh (without VAT);
Electrical Energy LLP installed capacity of the project is 1 MW, auction price is 41.17 tg/kWh (without VAT);
Turan Energy LLP has an installed capacity of 2.2 MW, the auction price is 41.18 tg/kWh (excluding VAT).
In order to comply with the requirements of the Rules for Organizing and conducting auctions, representatives of the Ministry of Energy of the Republic of Kazakhstan, JSC Institute for the Development of Electric Power Industry and Energy Conservation, USAID and AIFC participated as observers.
The register of winners of the auction for renewable energy can be found on the official Internet resource of the organizer of the auction: https://vie.korem.kz/rus/analitika/restr_pobed/
The next auction is scheduled for November 15, 2024 for the selection of projects for the construction of a wind farm with a total installed capacity of 100 MW.
The organizer of the auction is JSC "Kazakhstan Operator of the electric energy and capacity market".
Source : https://www.gov.kz/memleket/entities/energo/press/news/details/883713