Two dams were repaired in the Kobda district, and a drainage channel was built on the third dam

Two dams were repaired in the Kobda district, and a drainage channel was built on the third dam

04.03.2025 01:18:59 77

 


During a working visit to the district, the head of the region inspected the condition of the "Batys", "Saukayin" and "Ural-Oyil" dams.

According to the district akim Izgilik Tynymgereev, the repair work on both hydro structures was carried out by "Authority Construction Company" LLP.

In addition, the construction company built a water diversion channel on the "Ural-Oyil" dam, which is 4.9 kilometers long. A total of more than 900 million tenge was allocated for the work carried out on three projects. All three strategically important facilities will undergo technical and author's control.

Hydrotechnical structures with a total length of 9.2 kilometers will allow for effective regulation of water flows during spring floods and protect the district center from flooding.

After reviewing the condition of the dams, the regional akim instructed to strengthen control over the use of water diversion channels and dams to ensure their operation during the flood period. The district akim was instructed to develop an action plan to protect settlements from flooding and improve water drainage.

Source : https://www.gov.kz/memleket/entities/aktobe/press/news/details/948606