Planned road maintenance works continue in Bostandyk district
17.04.2026 14:48:38 467
Planned works are currently underway in Almaty’s Bostandyk District to carry out routine maintenance of the asphalt concrete pavement and eliminate defects across the district’s road network.
As of today, repair works have been completed on Klochkova, A. Kekilbayuly, and Turkebayev Street. Maintenance activities are currently ongoing on Prokofyev street, south of Abay Avenue.
In addition, to improve road safety and prevent hazardous situations, the replacement of more than 1,000 manhole covers of utility inspection chambers is scheduled.
The main scope of repair works is planned for April–May of this year, with further continuation throughout the summer period. These measures aim to enhance road traffic safety and improve the overall condition of the district’s transport infrastructure.

Source : https://www.gov.kz/memleket/entities/almaty-bostandyk/press/news/details/1203107?lang=kk