Nurlybek Nalibayev inspected the progress of social infrastructure construction in Kyzylorda

Nurlybek Nalibayev inspected the progress of social infrastructure construction in Kyzylorda

06.11.2026 04:10:37 294

First Deputy Prime Minister of the Republic of Kazakhstan Nurlybek Nalibayev, on behalf of the Head of Government, arrived on a working visit to Kyzylorda Region. Together with the region's Akim Murat Ergeshbayev, he reviewed the progress of construction of social and infrastructure facilities.
Currently, several new medical facilities are under construction in Kyzylorda. One of the largest projects is a 300-bed multidisciplinary hospital with an oncology department.
The medical complex will also include a polyclinic designed for 100 visits per shift. Construction funding has been allocated from the republican budget, and funds for completing the work are provided from the Infrastructure Development Fund.
The total area of the complex is about 48 thousand square meters. It consists of 10 blocks, which will house an admission department, intensive care, chemotherapy and radiology departments, operating rooms, a polyclinic, a boarding house, a physiotherapy department, and other units.
Interior finishing work, installation of utility networks, landscaping, and greening of the territory are currently underway. The construction of the facility is 85% complete.
The First Deputy Prime Minister also reviewed the progress of construction of Polyclinic No. 5, designed for 400 visits per shift. The total area of the building is 8,937 square meters. 9.8 billion tenge has been allocated for the construction of the medical facility.
To date, 65% of the work has been completed. Interior finishing, window installation, and laying of utility networks are actively underway. Medical equipment is planned to be delivered and installed by December 25. The facility is scheduled to be commissioned by the end of the year.
At the construction site of the 200-bed perinatal center, work on fencing the territory has been completed. Earthworks, foundation construction, and rebar tying continue.
52.8 billion tenge has been allocated for the implementation of the project. The three-story building with a total area of 39.1 thousand square meters will consist of 10 blocks. The project also provides for laboratory and food departments. The center is scheduled to be commissioned in March 2028.
At the Kyzylorda Arena sports complex, 90% of construction work has been completed. The complex is designed for 2,552 spectators and includes blocks of three to four stories.
The sports complex includes an Olympic-standard swimming pool, courts for futsal, basketball, and volleyball, as well as a 300-seat conference hall.
Interior finishing and design work, facade cladding, landscaping, and greening of the territory are currently ongoing at the facility.
In addition, the First Deputy Prime Minister reviewed the project for the construction of a pedestrian bridge across the SyrDarya River. The work is being carried out by the company Alem Qurylys AQ. 12.9 billion tenge is provided for the construction.
The bridge will be 319.4 meters long, with a width ranging from 6 to 12 meters in different sections. The structure will be equipped for convenient movement of both pedestrians and cyclists.

Source : https://www.gov.kz/memleket/entities/kyzylorda/press/news/details/1313949?lang=ru