Another settlement in Kostanay region was connected to gas
12.05.2026 18:16:20 138
About 2 thousand residents of the village of Diyevka in the Auliekol district have gained the opportunity to connect to gas supply networks.
The implementation of the project for the construction of a supply gas pipeline from the automated gas distribution station in the village of Auliekol to the village of Diyevka was carried out from August
2024 to October 2025.
«Today is an important event for the residents of Diyevka village. We are supplying blue fuel to homes. This is not just an infrastructure project, but a real contribution to improving people's quality of life», – said the Akim (Governor) of the Kostanay region, Kumar Aksakalov, at the ceremonial event.
The total estimated construction cost amounted to
2 billion tenge from the local budget. 56.3 km of gas pipeline were built.
To reduce gas pressure from high to low, four block-type gas regulator stations were installed.
For the gasification of the village, a project for the construction of gas distribution networks in Diyevka was also implemented, completed in October 2025.
The total estimated cost of the gas distribution network construction project amounted to 535.625 million tenge. 17.4 km of gas pipeline were built.
«On behalf of the elders and personally, I want to express deep gratitude to the Head of State, Kassym-Jomart Kemeluly Tokayev, the regional leadership, and all the specialists whose work made it possible to implement this large-scale project. Seeing the fruits of such care for villagers is a great joy. May warmth and prosperity always be in your homes with the arrival of natural gas», – shared the joy of the village elder, Kaby Kusainov.
Thus, the gasification level in the district will increase
to 51.8%.
It should be noted that currently in the district, 3 projects are at the implementation and development stage – these are the construction of gas distribution networks in the villages of Kushmurun (first phase), Novonezhinka, and Timofeyevka.
In the Kostanay region, out of 501 settlements, 87 are supplied with natural gas.
The total length of gas pipelines in the region is 5.1 thousand km, including distribution pipelines – 4.3 thousand km, and main pipelines – 819.7 km.
Over the last three years (2023-2025), approximately 8 thousand people have gained access to the gas supply network. The region's gasification level increased to 60.4% in 2025.
The implementation of the project in Diyevka village will have a positive impact on the socio-economic and environmental living conditions of the population, and will also contribute to housing construction and the development of agricultural product processing enterprises.

Source : https://www.gov.kz/memleket/entities/kostanay/press/news/details/1218251?lang=kk